owner

direction generale de l’equipement et du transport du grand casablanca

project

  • improvment of the sidi maarouf crossring in the center of casablanca (11’000 veh/hour)
  • implementation of the tramway line
  • conceptual and detailed design of a cable stayed bridge over the crossring - total length 225 m
  • conceptual and detailed design of the complete crossring with underpasses, cut and cover tunnels, considering the traffic during the entire work
  • preparation of the tender documents

design team: T ingenierie, greisch (liège), team maroc (rabat) and f. zirk architect

T engineering tasks

  • project management
  • conceptual and detailed design of the cable stayed bridge
  • coordination of traffic studies
  • construction cinematic
  • preparation of tender documents

structural description

  • double rundaround with underpasses
  • asymetrical cable stayed bridge with inclined pylon, main span 140 m bac span 50 m
  • central and unique stay fan in the main span, lateral stays in back span with counterweight abutment
  • composite deck with central steel box and concrete slab, concrete pylon

timeframe

  • conceptual and detailed design 2009-2010
  • construction 2014 - 2016