owner
state of geneva
department of public works
bridge division
project
project competition for the crossing of the lake in geneva - switzerland
scope of work of T ingénierie sa
general manager of the multidisciplinary projet team
main bridge conception and design
competition won in 1995 with a cable stayed and a suspended solutions
specifications
- curved cable stayed bridge with a single central suspension
- three main spans of 350 m each, two adjacent spans of 176 m each
- concrete box section
- self balanced bridge, horizontal soft stabilisation by its own piles
- access bridges with spans from 36 m to 56 m
- depth of foundations : 75 m below lake bottom
- connection to right shore over an artificial island and through a cut and covered immersed tunnel 800 m long
- total cost : chf 280'000'000.--
- detailed project has been completed
schedule
project refused by popular vote in june 1996