Projects

owner

state of geneva

department of public works
bridge division

project

project competition for the crossing of the lake in geneva - switzerland

scope of work of T ingénierie sa

general manager of the multidisciplinary projet team
main bridge conception and design
competition won in 1995 with a cable stayed and a suspended solutions

specifications

  • single central cable suspended bridge
  • main span of 950 m
  • composite box section
  • central suspension of the deck
  • cable with varying section made of individually protected strands
  • transversal stabilisation by torsion of the deck and contribution of the restraint forces due to the cable (purely non linear behaviour)
  • liaison fixe du câble et du tablier au centre
  • connection to left shore through a cut and covered tunnel used as anchoring
  • connection to right shore over an artificial island and through a cut and covered immersed tunnel 800 m long

schedule

project refused by popular vote in june 1996