owner
State of vaud - switzerland
public roads department
project
twin bridges in prestressed concrete erected by balanced cantilever method
curved layout, on the highway between lausanne and
bern
scope of work of T ingénierie sa
civil engineers joint venture :
gvh, bg bonnard & gardel, T ingenierie sa, c. notheisen
scope of work of T ingenierie sa :
- conceptual design for the competition
- project competition won in 1994
- calculation of prestressing losses during erection phases
specifications
- overall length : 570 m
- max height over ground level : 120 m
- spans of 93 m, 135 m, 150 m, 120 m, 70 m
- free cantilever bridge, cast in place with temporary stays between piers during erection
- foundations on piles, blocks and shafts
- total cost : approx. chf 38’000’000 .-
schedule
construction 1996 - 1999